Module: Production & Manufacturing Prerequisites: Finished goods and components set up as stock items

The production tools help you plan what you make and record what it used. You define a bill of materials (BOM) for each finished product, plan runs with work orders, record the components consumed and compare plan with actual. Quality Control records inspections on goods received and on work orders. This guide also says clearly where production does not move stock or post to the ledger, so you know what to do by hand.

Build a Bill of Materials

1
Create a BOM version

Go to Operations → BOM. Choose the finished good, the quantity one run produces and the unit of measure. Each BOM has a version number, so you can keep a history of recipe changes.

2
Add components

Click + Component and add each raw material or sub-assembly with its quantity. Enter a scrap percentage to allow for waste; for example, 5 means 5% more of that component is planned. A component that has its own BOM is marked as a manufactured item.

3
Activate or clone

Click Activate to make a version the current recipe for that product. Use Clone to copy a version, with all its components, into a new inactive version that you can change.

4
Explode the BOM

Use Explode to work out the total raw materials needed for a production quantity, across all levels of sub-assemblies.

Run Work Orders

1
Create the work order

From a BOM version, click Work Order, or go to Operations → Work Orders. Enter the quantity to produce, the warehouse and planned start and end dates. The system fills in the component lines from the BOM, scaled to the quantity and including the scrap percentage.

2
Move it through its statuses

A work order moves from Draft to Released, then In Progress, then Completed. It can be cancelled at any point before it is completed.

3
Record what was used

On the work order, enter the quantity actually consumed and the unit cost for each component line. You can add extra lines while the order is open. Completed and cancelled orders are locked.

Work orders do not move stock

Work order statuses and consumption lines are records only. They do not issue components from stock, receive finished goods or post to the general ledger. Update stock by adjustment on each item (stock journal only), and ask your accountant to post any journal needed for the value.

Compare Plan with Actual

Go to Operations → Ops Reports and open Work Order Variance. For each completed work order it compares the planned component use with what you recorded:

MeasureHow it is worked out
Component varianceQuantity consumed less quantity required, per component
Cost varianceConsumed quantity × unit cost, less required quantity × unit cost

Quality Control

1
Create an inspection

Go to Operations → Quality Control and create an inspection linked to a goods received note or a work order.

2
Record results per line

For each line, enter the quantity inspected, passed, failed and quarantined. The three results cannot add up to more than the quantity inspected. Set the result to pass, fail or quarantine, and choose a disposition: return to supplier, scrap or rework.

3
Submit

When you submit, the inspection becomes Passed, Failed or Partially Passed based on its lines. Failed and quarantined inspections are listed on Operations → Ops Reports.

Inspection results are records

An inspection does not move stock by itself. To hold a batch back, set it to quarantine under ERP → Stock Batches. Returns to a supplier are handled with a supplier debit note under Finance → Supplier Notes.

Simple Recipes

For simple assembly there are also stock recipes: a list of components for one finished item. Running "produce" on a recipe issues the components from stock and receives the finished item. This is written to the stock journal only, with no ledger posting. Recipes are currently available through the API, not on a menu screen.